When working in an environment such as a school, we understand the importance of listening to the Client's needs at the outset, to ensure that any disruption caused by our works is kept to the absolute minimum. Close liaison with the Client throughout the contract ensures that any queries or problems are dealt with promptly and efficiently, either by our experienced Site Agents and/or Contracts Manager or by a Company Director.

As with Trevor before him, Andrew is a governor at a local school. We have held a close relationship with this school for over 30 years and this liaison allows us to keep abreast of current regulations and requirements.

We have a proven track record of delivering major contracts within tight deadlines.

 

West Lea School, London N9

West Lea School, London N9

Internal refurbishment of classrooms and offices including complete fit out of new furniture at West Lea School, London N9

- Client: West Lea School
- Contract Administrator: DHP
- Contract Duration: 6 weeks
- Contract Value: £230,000
- KPI Score: 58/60

 

Reference from West Lea School

 

St Albans Girls School, St Albans

St Albans Girls School, St Albans

Replace cladding panels and window walling at St Albans Girls School, St Albans

- Client: St Albans Girls School
- Contract Administrator: Kier Workplace Services Ltd
- Contract Duration: 20 weeks
- Contract Value: £820,000
- KPI Score: 59/60

Reference from St Albans Girls School

 

 

 

New Maths, Science & Technology Block, Sandringham School, St Albans

St Michael's School, Newland Construction, building in Hertfordshire and surrounding areas

 

- Client: Sandringham School
- Contract Administrator: Property Tectonics
- Contract Duration: 50 Weeks
- Contract Value: £2.7 million
- KPI Score: 60/60

Reference from Sandringham School

 

 

New Kitchen & installation of modular Building at Oakthorpe Primary School, Enfield

St Michael's School, Newland Construction, building in Hertfordshire and surrounding areas

 

- Client: London Borough of Enfield
- Contract Administrator: BHP Architects
- Contract Duration: 18 Weeks
- Contract Value: £414,510
- KPI Score: 60/60

Reference from Oakthorpe School

 

 

 

Removal of existing Roof & Construction of a 1st Floor timber clad extension with stairs & Lift at Phoenix Arch School, London NW10

St Michael's School, Newland Construction, building in Hertfordshire and surrounding areas

 

- Client: Phoenix Arch School
- Contract Administrator: dm3 Architecture
- Contract Duration: 32 Weeks
- Contract Value: £400,000
- KPI Score: 58/60

Reference from Phoenix Arch School

 

 

Woodfield School, Kingsbury, NW9

Construction of new changing room block incorporating toilets and showers..

- Client: Governors, Woodfield School
- Contract Administrator: Ian Caudell Architects
- Contract Duration: 16 weeks
- Contract Value: £300,000.00
- KPI Score: 60/60

Reference from Woodfield School

We have subsequently carried out two more successful projects direct for the School.

Arnold House School, St John’s Wood, NW8

St Michael's School, Newland Construction, building in Hertfordshire and surrounding areas

Removal of existing roof and formation of two classrooms and two practice rooms for the music department. New staircase and glazed link to adjoining school building.

- Client: Arnold House School
- Contract Administrator: Bob Philips Consult Ltd
- Contract Duration: 22 weeks
- Contract Value: £400,000.00
- KPI Score: 58/60

Reference from Bob Philips

 

 

Haileybury College, Hertford Heath

Haileybury, Newland Construction, building in Hertfordshire and surrounding areas

The design and build of a two storey modern languages centre. Comprising fully glazed entrance foyer, 14 classrooms, toilets and stores with heating provided via a ground source heat pump.

- Client: Haileybury College
- Newland Architect: Wastell & Porter
- Newland Engineer: Stuart Thomas Associates
- Contract Administrator: Ainsley & Partners
- Contract Duration: 52 weeks
- Contract Value: £1.5 million
- KPI Score: 59/60

Reference from Haileybury College

St Michael’s Catholic Grammar School, Finchley

St Michael's School, Newland Construction, building in Hertfordshire and surrounding areas

Demolition of attic 2nd floor and construction of new 2nd floor comprising four classrooms, corridor and toilets.

Classroom below remained in use throughout the contract.

- Client: St Michaels Catholic Grammar School
- Architect: Roger Bennett
- Quantity Surveyor: Monk Dunstone Associates
- Contract Duration: 40 weeks
- Contract Value: £840,000
- KPI Score: 58/60

This is just one of four successful projects we have undertaken for this school

Reference from St Michael’s Catholic Grammar School, Finchley

 

 

Albury C of E JMI School

Albury School, Newland Construction, building in Hertfordshire and surrounding areas

Construction of new school hall. Comprising of main play area, kitchen, toilets and stores, with glulam trusses and beams

- Client: Diocese of St Albans
- Architect/Surveyor: Wilby & Burnett
- M&E Consultant: W R Associates
- Contract Duration: 30 weeks
- Contract Value: £475,000
- KPI Score: 60/60

 

Albury School, Newland Construction, building in Hertfordshire and surrounding areas

Beaumont School, St Albans

Beaumont School, St Albans

Extension to provide additional 6th Form and library accomodation

 

- Client: Beaumont School
- Contract Administrator: Property Tectonics
- Contract Duration: 33 Weeks
- Contract Value: £600,000
- KPI Score: 58/60

Reference from Beaumont School

Lochinver House School, Potters Bar

Construction of a 2 storey extension to provide 2 additional classrooms,
changing rooms and showers

- Client: Lochinver House School
- Contract Administrator: Ainsley & Partners
- Contract Duration: 31 Weeks
- Contract Value: £760,000
- KPI Score: 58/60

Reference from Lochinver House School