We have the skilled craftsmen and specialist knowledge to undertake a variety of special works – whether it be restoring a Grade II listed property or installing the latest sustainable building products.
This is one of numerous successful refurbishment properties we have undertaken for The Wellcome Trust
- Client : The Wellcome Trust
- Architect : Savills UK
- Contract Duration : 20 weeks
- Contract Value: £480,875
- KPI Score: 60/60
Complete refurbishment ofa 16th Century former coaching inn, into modern offices whilst maintaining as much of the original fabric of the building as possible.
During the works, highly significant early 17th century painted plaster frescos were uncovered on the main chimney stack. The stack had a major crack in the brickwork which had to be carefully repaired without causing any damage to the mural.
- Client: Green Energy UK
- Architect & Contract Administrator: Wastell & Porter (proposed by
NC)
- Interior Designer: Newland Interiors
- Contract Duration: 21 weeks
- Contract Value: £320,000.00
- KPI Score: 58/60
This project was a winner of the 2012 HAA Architecture Awards in the Conservation
and Restoration Category.
We worked with our sister company, Newland Interiors, to carry out the final fixtures and fittings which included purpose made work desks.
Bespoke single storey extension to provide a new kitchen, utility, dining area and garage. Cantilevered floor to carry external patio area, sips panels to form external walls with Oak cladding and copper roof. Carried out repairs to existing single glazed two-storey cube abutting Grade II Queen Anne House.
- Client: Confidential
- Contract Administrator: Projekt Solutions
- Contract Duration: 28 weeks
- Contract Value: £525,000
- KPI Score: 53/60
Formation of new masonry amphitheatre within existing playground. Project received commendation at the Brick Awards
- Client: London Borough of Barnet
- Architect: Tim Foster associates
- Contract Duration: 6 weeks
- Contract Value: £65,000
- KPI Score: 59/60
External swimming pool and pergola with associated hard landscaping
- Client: Private Clients
- Contract Duration: 12 weeks
- Landscape Designer: Julie Wyse
- Contract Value: withheld
- KPI Score: 59/60